Saturday, December 20, 2008

This week has proved to be a busy one at the homesite! Monday Jeremy went up to do the walk-thru and then he was back up a few days later to drop off a few more items that we needed in the bathrooms. Well, the biggest things that need to be completed now are the carpet and a final coat of finishing paint. The electrician does need to come back and finish his work, so he has maybe a full days' worth of work left as well. But the plumbing is nearly done, so we now have running water and toilets that flush! The plumbers took care of all of that Wednesday of this past week. They ran into one small "snag," but it's in our favor since it involves getting a smaller sink for the half bath than what was originally ordered. So they need to come back to install that- hopefully this week! It's down to the finishing touches now! We were originally told we could take posession on January 1, 2009, but scheduling the painters has been tough since they're booked, and the cleaning crew needs to come in and clean before we move in, so our official move-in date is now January 3, 2009. That's fine with me since the third is a Saturday and it would be better for us to move on a weekend since we are doing it ourselves (with a little help from our friends!). Anyway... here are some pictures from our trip to the homesite today:

This is the finished fireplace! Watching the stone crew put all the stone in place was definitely a sight to see! They were so efficient and good at what they do that it seemed like it took all of two minutes to complete the job- even though I know it took much longer than that. We are SO pleased with the outcome. Doesn't it look like it's just asking for us to have a fire in it?

My mom was in this one- Hi Mom!!! I was getting a picture of the finished countertops with the kitchen sink installed, too. The countertops are covered with corrugated board to protect them from any tools that may be around and will be removed by the cleaning crew when they come in to do the final cleaning. But you can see exposed parts of the counter, and I really like it! The open space in the cabinets on the right side of the picture is the opening for the dishwasher. It will be delivered this week. Hopefully it coordinates with the plumbers' return to finish the half bathroom sink. We'll see!


This is the guest/kids' bathroom. You can see the toilet is now in, and the countertops and sinks are also installed. Yes, there are two sinks in this bathroom. Double cleaning duty here, too... But at least I won't have to listen to the kids fighting over who dirtied the sink- they will each be responsible for their own!

Another view of the guest/kids' bathroom. You can see in the reflection from the mirror that there is a closet behind the bathroom door. It's a rather spacious closet, so there will be plenty of room for towels, washcloths, tp, and other bathroom necessities... with lots of space left over, I'm sure!

This is the master bathroom. YAY! We have two sinks in here, too. I guess I really have quadruple cleaning duty, don't I? Oh well... I'll get used to it! The countertop in here honestly looked a LOT more blue to me when we picked it out... but now I have to confess that it does look more green. That's okay- I like it anyway! And I'm still using blue towels in our bathroom!

This is our finished master shower. We opted for a door to the shower over a shower curtain rod. I know it may be a bit more work to keep clean, but I'd rather that over replacing shower curtain liners all the time. Besides, I like the look of this, too. There is still a small amount of tile work to be done around the bathtub, but I believe that this is going to take place this coming week, also.

Finally, here is the laundry room utility sink. Jeremy REALLY wanted one of these, and I thought it would be a good idea, too. Considering we have some space for us to get dirty outside, a utility sink is great for rinsing off the bottom of boots and such. I'm pretty sure we'll be thanking ourselves for this little tidbit later on!

Well, that's really about it for this visit. By the end of this holiday week we hope to see that the only things left to do are carpet, paint and the final cleaning. It's getting close now! There most likely won't be any updates between now and Christmas, so....

Merry Christmas!!!

Be sure to check back after Christmas as we'll most likely have one more update before the big move. Then, once we get moved in we'll post pictures of the "finished" move... MAYBE even add a video tour!

Tuesday, December 16, 2008

It's nearly done now!

So Jeremy gets a phone call yesterday while he is working asking him if he can go to the homesite and do the walk through with the foreman for our build. And you know what? He took care of it yesterday afternoon! Before he went I made a list of things for Jeremy to go over with the foreman so all of our questions would be answered about things that still needed to be done and a couple of things that needed to be changed. In my last post I listed a few things that I was skeptical would happen before we move, but Jeremy was told again yesterday that we will, indeed, be moving over New Year's! Up to this point I have really enjoyed watching the whole building process and I've tried not to get too overly excited about things for fear of being let down somehow. But I'll be honest now and say that these builders have not let me down once! The craftsmanship is spectacular, the contractors have all been super to work with, and ANY questions and concerns we've had have always been addressed promptly. I would definitely recommend this builder to ANYONE who wants to build a home!!!

Jeremy came home with my list and he had written answers on it so he could remember what he was told about when things were happening now that it's all wrapping up. We only had 3 concerns at this point, and each of them have been addressed. The last two windows to go in came with full screens instead of half screens that can slide up and down, so new half-screens are being ordered to replace the full ones. The basement door doesn't latch to stay closed, so the strike plate is going to be moved so that it latches properly. Perhaps the biggest concern was one I noticed the other night when we were there. The master bathroom has a separate room for the toilet and I noticed that the doors had all been hung, so I was opening and closing all the doors and noticed that the WC (that's water closet) door swung IN rather than OUT. Now if the WC room was longer it wouldn't be a problem, but since the toilets haven't even been installed yet I don't think the guy who hung the doors realized it would be a problem. You see, if you opened the door all the way and then installed the toilet you would never get the door to close again because it would just hit the side of the toilet... Originally that door was supposed to swing OUT and for some reason it got marked incorrectly... so now they're going to change the hinges and make it swing out so we can actually get into the WC!! Yep- as for concerns, they aren't very big, and seriously, those and the back patio decking (which was already fixed) have been the ONLY concerns we've had!

As far as finishing "touches" go, the stone work around the fireplace gets done today, gravel out front so we can drive our vehicles into the garage gets put down today, the plumber returns tomorrow to install sinks, toilets, and other plumbing fixtures, they're adding a deadbolt lock to the front door before we move in, the painters return to do a final coat on 12/27/08, and the carpet gets installed 12/29-12/31! An attic scuttle hole will be added so we have attic access and a dryer vent will be added sometime between now and when we take possession, too. The electrician will be returning to install the vanity lights in the bathrooms, so we will be purchasing them this week. I didn't mention countertops and trim... Well, that's because they're DONE! Jeremy sent me a picture from his phone yesterday of the countertops in the kitchen and I was jealous that I didn't get to see the finished kitchen counters with him. He said they finished the trim work yesterday, too. WooHoo! It's all coming together and it just looks SO nice!

The closets have nothing in them yet, but Jeremy did say that the gentleman who does the closet shelving will call to set up and appointment with me to go over what I want in the closets. I'm not too concerned- I have an idea already, so it should be a short and sweet appointment! We'll see- I'm hoping he calls today or tomorrow. I'd LIKE to get up there before Friday, but we'll see how it goes.

Well, that's it. No pictures for this entry. We'll be taking my mom and dad to see the house this weekend since they're coming in for Christmas (YAY!!!), so I'll get some pictures then. Until then, stay tuned- don't forget to check back early next week to see the newest pictures!!

Saturday, December 13, 2008

Little Details...

We went up to the homesite earlier this week and were excited to see that the hardwood flooring had been installed in the entry and study. It hadn't been stained yet, but it was all installed! The trim work was about one third finished at that point, too. A few of the interior doors had been hung as well, but it just looked like a LOT was left to do. Jeremy and his best friend Chuck took Michael today and delivered the stove to the house, so they got to see what else had been accomplished this week. I was anxious to see it, myself, so when Megan woke up from her nap, we took off to meet them up there (all this after spending the day running errands!). I was expecting to see countertops, but I also had a feeling that they most likely wouldn't be there. That second feeling was the correct one. The trim work is nearly complete, but until it is the countertops won't be installed. Maybe this coming week? We'll see. At any rate, the hardwood flooring has been stained- and boy does it look NICE!!! The treads for the stairs down to the basement have also been done and they look great, too! It's amazing what the little details like trim work and doorknobs will do for a home! Here are a few pictures from our trip to see the house today:

A view of the kitchen from the dining area. The door leading into the study has been put up! In the lower left of the picture is an item wrapped in white plastic- it's the stove. We've been asked to leave the appliances in the dining area until the builders are ready to move them to their rightful "homes" in the kitchen.

This view is of the living room with the trim around the window and sliding door to the back patio. I was under the impression the stone work around the fireplace would be done this week, but obviously that didn't happen. Not sure if I heard Jeremy wrong or he meant that it would take place this coming week. Again... we'll see!

Here is a view of the closet doors in Megan's bedroom. I'm simply amazed at the elegant simplicity in the finished look of the doors here! The trim around the window and door leading out of her room is also finished. The only trim left to put up in the bedrooms is the trim along the floor.

This is a view of the pantry doors from the kitchen. I couldn't even fit the doors in the picture completely due to the door frame! I'm looking forward to using this pantry- it's nice and wide and has great lighting, so I should be able to keep it organized and stocked.

Ah- the study floor!! Doesn't this just look great?!?! I am SO impressed with how wonderful the flooring looks here! Not only that, but when you look at the flooring from the living room (since the carpet isn't installed yet), you can see just how thick the flooring is! We asked the builder to have the flooring stained a bit darker than the cabinets so it wouldn't blend together too much. I love the way it turned out- it's just dark enough to be offset from the cabinets and our furniture, yet light enough to blend in perfectly with the rest of the house!

Well, it seems to me that there is still a LOT to be done- and I wonder if we really will move when they say we can, but we'll see. This is just some of the stuff that needs to be finished:
- trim work
- stone work around the fireplace
- mantle put up over the fireplace
- electricians need to finish wall plates and lights in the bathrooms in addition to any other electrical connections that haven't been completed yet.
- plumbers need to install the sinks, toilets, and faucets
- hot water heater needs to be installed
- carpet needs to be installed
- attic scuttle hole needs to be cut and ladder installed
- dryer vent needs to be cut in laundry room
- countertops need to be installed
- appliances put in their "homes" in the kitchen
- Geothermal system powered ON
- hand rails installed along stairs to basement
- painters return to do a final coat of paint
- general clean-up in and around the house

I know there is probably more that needs to happen, but that's all I can think of right now. Jeremy says it won't take all that long since they tend to be quick with their work- and darn good at it, too- but it just seems like a lot to me and makes me wonder if we REALLY will be moving when we were told and not a week or two later. Well, the only thing I can say is- I'll check back at the end of this week and we'll see how much more gets accomplished toward getting the house completed. So until we get more pictures and an update... sit tight... but don't forget to check back!!


Sunday, December 7, 2008

Cabinets!

We now have cabinets!! Earlier this week we headed up to the house because we needed to bring something up for the electrician and when we walked in I noticed a cabinet in the half bathroom. We saw the truck outside but didn't realize it was the cabinet crew- we thought it was the gentleman doing the trim. Boy were we wrong! We looked in every room and were simply amazed at the craftsmanship of all the cabinets! Countertops and crown molding for the tops of the cabinets will be finished this coming week, but what we've already seen is amazing! The trim and doors have been delivered to site and should be going up this coming week, too! The stone work around the fireplace will be done this week and the painters will return to do a final coat once that is all done. The appliances will arrive next weekend (and one on 12/24) and then the carpet gets installed roughly a week before we move in- it won't be long now! Jeremy went up to get some things and got some pictures yesterday, so here they are:

Here are the built-ins in the study. This should be a great starting point for us to put all of our books out... (I HOPE!!)

This view is looking into the kitchen from the edge of the living/dining room. As you can tell, the countertops are not there, but they will be this coming Friday! I LOVE the woodwork!

Jeremy took this picture to show that the lower cabinets have slide-outs- that sure will make it easier when it comes to getting pots and pans out for cooking dinner!

This view is where the microwave and stove will go. The microwave hood will be delivered this weekend, and the refrigerator will, too. We just have to find the time to get the stove up there since it is currently in our shed... hopefully we can get that up there this weekend, too!

This view of the kitchen is from the doorway into the study. You can see where the sink will go and where the dishwasher will be. The dishwasher should be delivered right before Christmas, so we'll have to get that hooked up- but no biggie there. I'm just looking forward to seeing the kitchen completed!

Here is the other view of the kitchen from the doorway to the study. This is simply cabinets and a counter- I know I'll use the space!!

This is the master bathroom. There will be a sink on each side- it's just going to be double the cleaning duty here...

A view of the front covering the tub in the master bathroom. I can't wait to see this part finished, either!

These are the finished cabinets in the laundry room. This is double the space I currently have... I just wonder if the extra space will stay empty or if we'll actually find something to put up there?

Jeremy got this great picture of the trim stacked up in Megan's bedroom. And this is only about HALF of the trim for the house! The other half is in the living room, but this picture came out looking much "cooler" in my opinion.

Here are the doors for the house. They are currently stacked up vertically against a wall in Michael's bedroom. There are other doors against other walls in the house, but this was a pretty cool picture, too.


Last, but not least, I had to include this picture. I have wanted to get a picture of the back of the house for some time now, but it's been WAY too muddy out there. It happened to be snowing and the yard was pretty frozen, so Jeremy turned on all the lights (not that it's easy to tell) and went out back and got this picture. It just makes the house look so big! Honestly, it's not all that big- it's just the basement that makes it look so huge. The only thing missing from this picture are the lights that go outside the basement doors. Those still need to be installed, but they will be soon. There are still a few finishing touches that need to be done with outlets and such, so those will be done within the next couple of weeks.

I'm not sure when I'll be heading back up to the homesite, but I'm anxious to see what progress is made over the course of this week. Hopefully I can get out there this weekend, but we'll see. Just keep checking back for more updates!